The Steps of Architectural Design and the Building Permit Process

How a house or a building is designed, from the first sketch to the building permit, step by step and through an architect’s eyes.

Designing a house or a building rarely starts and ends with a single drawing. It is a chain of connected steps that runs from reading the site to the building permit and on to the construction details. The decisions made at each step shape the next one. In this article we walk through the architectural design process and the permit stages in Türkiye, in order.

1. First Meeting and the Brief

The process starts with getting to know you and what you expect. How many people will live in the house, how many bedrooms are needed, is there a need for space to host guests, to work or for a hobby? How does your day flow? Budget and schedule are discussed at this stage too. From this we write the brief, the list of spaces and their sizes.

2. The Site and Its Zoning Status

Before design begins we need to know what the site allows. The zoning status document issued by the municipality shows how much can be built on the plot:

  • TAKS: the ratio of the building footprint to the plot area
  • KAKS (floor area ratio): the ratio of the total floor area to the plot area
  • Height and number of storeys: the maximum height the building can reach
  • Setbacks: how far the building must stay from the road and the neighbouring plots
  • Building order: detached, attached or block layout

The title deed is also reviewed at this stage. A surveyed site plan prepared by a licensed surveyor and a soil investigation report are needed later for the permit. Nothing replaces seeing the site in person, though. The slope, the path of the sun, the views, the wind, existing trees and neighbouring buildings are the real inputs of the design.

3. Concept Design

The concept is the main idea of the building. How the volume sits on the site, how the rooms face the sun and the view, and how inside and outside relate to each other are decided here. Different options are tested with sketches, massing studies and 3D models.

Photorealistic architectural visualization makes these decisions much easier. Before anything is built we can see the light, the materials and the feeling of the space, and set the direction together.

Aerial view of G Güneş House: the gabled volume, its glazed end and terraced stone garden walls
From concept to building: G Güneş House, Çatalca

4. Preliminary Design

The chosen concept becomes the preliminary design. Plans, sections and elevations are usually drawn at 1:100. Room sizes, door and window positions, stairs, wet areas and the overall dimensions of the building are fixed. The preliminary design is the agreement between client and architect. Major changes after this stage cost both time and money, so it is worth approving it without haste, imagining yourself living in every room.

5. Permit Drawings

For the building permit, drawings from several disciplines are prepared alongside the architectural set:

  • Architectural drawings
  • Structural drawings (reinforced concrete or steel)
  • Mechanical drawings: plumbing, heating and ventilation
  • Electrical drawings
  • Thermal insulation calculation and other required reports

The drawings must work together. Making sure structural columns do not clash with the architectural plan and that service shafts are in the right place is resolved in the permit set. Every conflict left to be solved on site comes back as a problem during construction.

6. Building Inspection and the Building Permit

Together with the drawings, a contract is signed with a licensed building inspection company and a site manager is appointed. The municipality reviews the drawings, the required fees are paid and the building permit is issued. How the application is made and which documents are required can vary from one municipality to another.

The permit has a time limit. Under the Turkish Zoning Law, the permit lapses if construction does not start within two years of the permit date, or if construction that has started is not completed within five years. Plan your schedule around these limits.

7. Construction Documents and Details

The permit set shows that the building can be built. The construction documents explain how it will be built. Plans at 1:50, details at 1:20 and larger, window and stair details, façade and roof junctions and material schedules are prepared at this stage. The interior design is usually developed in detail at this point as well.

The more detailed the construction documents are, the more comparable the contractors’ bids become, and the fewer surprises there are on site.

8. Construction and the Occupancy Permit

Construction proceeds under the supervision of the building inspection company. When the architect who designed the project also follows the site, decisions made during construction stay true to the design. Once construction is complete, the required documents are finalised and the occupancy permit is issued.

What to Keep in Mind

  • Learn the zoning status before design starts. A design made without knowing what can be built may be wasted effort.
  • Approve the preliminary design without haste. This is the cheapest stage to make changes.
  • Pay attention to coordination between the permit drawings.
  • Put the permit’s start and completion deadlines in your calendar.
  • Do not skip the construction documents. Ask contractors to bid on the same set of drawings.
  • Decide by seeing. Renders and 3D models are the easiest way to spot mistakes before construction.

As with G Güneş House in Çatalca, we start every project from the site itself and run the whole process in one team, from concept to construction. Get in touch with us for a new building or a renovation.

This article is for general information only. Regulations and municipal practice change and vary from place to place, so check the current requirements with the relevant municipality and professionals.