Urban Regeneration in Türkiye: The Steps and What to Watch For

From the risky building assessment to the keys of the new apartment, the urban regeneration process step by step and through an architect’s eyes.

Urban regeneration in Türkiye replaces buildings that are not earthquake resistant with safe, liveable new ones. Managed well, it raises the value of the building and brings new life to the neighbourhood. Managed badly, it can lead to long delays, disputes between owners and apartments that fall short of expectations. The stakes are high in Istanbul. According to the 2019 earthquake loss estimation study by the Istanbul Metropolitan Municipality and the Kandilli Observatory, a magnitude 7.5 earthquake would leave about 48,000 buildings heavily or very heavily damaged. In this article we explain the process step by step and what to watch for at each stage.

1. Risky Building Assessment

The process begins with determining the building’s earthquake risk. The assessment is carried out by institutions licensed by the Ministry of Environment, Urbanisation and Climate Change. Any single owner can apply on their own. The institution takes core samples of the concrete, examines the reinforcement and prepares a report.

If the building is found to be risky, the report is sent to the relevant directorate and a risky building annotation is added to the title deed. Owners have the right to object to the report. The objection must be made within 15 days of the notification. This deadline is strict, and the right to object is lost if it is missed.

2. The Owners’ Agreement

After the risky building decision, the owners decide how the building will be rebuilt. This does not require unanimity. Since an amendment made by Law No. 7471 in 2023, a simple majority of the owners by share is enough. A two-thirds majority was required before. The meeting sets out the general framework of the new project, the choice of contractor and how the new building will be shared.

Watch out: the most common mistake at this stage is agreeing straight away with the first contractor who makes an offer. First learn the zoning status and building rights of the plot. That way you negotiate knowing how many apartments and how much floor area the new building can have.

3. Evacuation and Demolition

Once the owners agree, the building is vacated and demolished within the period set by the authorities. During this time, eligible owners and tenants may receive rent assistance. Demolition must be licensed and carried out safely, which also matters for the neighbouring buildings.

4. Choosing a Contractor and the Contract

The land-for-flats construction contract is the most critical document of the process. It should be signed before a notary and clearly cover:

  • The net and gross area, floor and orientation of the apartment each owner will receive
  • A detailed specification defining the materials by brand and grade
  • The delivery date and the penalty for delays
  • The guarantee the contractor provides, and who pays the rent assistance and how
  • How common areas, parking and any commercial units are shared

Visit projects the contractor has completed, and look into their financial strength and their building inspection record.

5. Design and Permits

The architectural, structural, electrical and mechanical drawings of the new building are prepared. A soil investigation is carried out and the drawings are submitted to the municipality for the building permit.

The architectural design is the home you will live in for years. It should be designed to live well, not only to fit in the largest number of apartments. Daylight, ventilation, room proportions, ceiling height, the façade and the quality of materials are decided at this stage. Having the design prepared or reviewed by an independent architect who looks after the owners’ interests makes a big difference at the end of the process.

Photorealistic architectural visualization and renders are very useful here. Owners see how the building and the apartments will look before construction, so decisions are made more easily and with fewer disputes.

Corner block of Valora Park Residences with shops on the ground floor and apartments above
Mixed use in urban regeneration: Valora Park Residences, Silivri

6. Construction and Inspection

Construction proceeds under the supervision of a building inspection company. Building inspection is mandatory, but having a construction manager who separately checks the materials against the specification and the quality of workmanship on behalf of the owners gives real peace of mind. A problem noticed on site is far easier to fix than one noticed after the building is finished.

7. Occupancy Permit and Title Deeds

When construction is complete, the occupancy permit is obtained and condominium ownership is established. Apartments should be handed over according to the areas and specification in the contract. Before handover, check each apartment for area, materials and workmanship, and report any shortcomings in writing.

State Support: Grants, Loans and Exemptions

Several important forms of support reduce the cost of urban regeneration:

  • The “Half from Us” (Yarısı Bizden) campaign: run by the Ministry of Environment, Urbanisation and Climate Change for risky buildings in Istanbul, it provides 875,000 TL as a grant, 875,000 TL as a loan and 125,000 TL moving support per home, 1,875,000 TL in total. For commercial units the grant and loan are 437,500 TL each, with the same 125,000 TL moving support. The campaign has been extended to 31 December 2026.
  • Area-based projects: in area-based regeneration projects run by TOKİ or Emlak Konut, owners receive an 875,000 TL grant and 125,000 TL moving support. This model has no loan component.
  • Low-interest loans: owners of risky buildings can use the World Bank supported urban regeneration loan of up to 3 million TL on favourable terms. This is separate from the Half from Us package.
  • Rent assistance: owners who leave their homes during demolition receive rent assistance under certain conditions.
  • Fee exemptions: under Article 7 of Law No. 6306, title deed transactions within urban regeneration are exempt from title deed fees, and municipal procedures such as the building permit and zoning status are exempt from the related fees.

Amounts and conditions are updated from time to time, so confirm the current details with the Ministry and your municipality before applying. Grants and loans strengthen the owners’ hand when negotiating the contract and the budget, so find out which support you are eligible for before agreeing with a contractor.

In Short, What to Watch For

  • Learn the zoning status and building rights before negotiating.
  • Sign the contract before a notary and spell out areas, the specification, the delivery date and the delay penalty.
  • Judge the architectural design by quality of life, not only by the number of apartments.
  • Have construction followed independently on behalf of the owners.
  • Inspect the apartments in detail before accepting them.

Valora Park Residences, which we designed in Silivri, is a mixed-use project bringing together residential, commercial and office functions as part of an urban regeneration initiative. Get in touch with us for the architectural design, visualization or construction management of your building’s regeneration.

This article is for general information only and is not legal advice. Regulations and practice may change, so get up-to-date information from the relevant institutions and professionals before making decisions.